title
Amend Court Order No. I.11. Dated December 12, 2023 Design Services for Improvements to the Water Treatment Plant at the Sheriff’s Office
end
body
Amend Court Order I.11. dated December 12, 2023 in order to capture the full amount of the design services proposed by Baxter & Woodman, Inc. of Houston, Texas, who was the awarded vendor for the project.
The amount was originally stated as not to exceed $502,311.00. However, that did not include the preliminary engineering services stated in the attached court order summary of $62,634.00. The total for the entire design and preliminary engineering services is a not to exceed amount of $564,945.00, per the attached proposal.
Further, that the funding for the project is utilizing ARPA funds.