Title: Issue Change Order for CSP #26-56 Hastings Roadway and Drainage Improvements Phase II
Indexes: Change Order, Expenditure
Attachments: 1. Hastings Ph 2 Package
Related files: 18743
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Issue Change Order for CSP #26-56 Hastings Roadway and Drainage Improvements Phase II

end

body

Permission to issue change orders to Greater Houston Construction, LLC of Houston, Texas to perform required work ensuring the project complies with the rules and regulations of Brazoria County and adding $94,246.66 (4.44%) to the original contract for CSP #26-56 awarded by Court Order No. I.6. on August 25, 2026; and

 

Whereas, a copy of applicable Change Orders in the amount of $94,246.66 and memo from the resident engineer Halff Associates, Inc. are attached; and

 

Whereas, funds for this expenditure are available via the grant contract with GLO.

 

Further, a certified copy of this order be furnished to the County Engineer for distribution to all parties involved.