File #: 15738    Version: 1
Type: Discussion - Engineer Status: Adopted
File created: 5/7/2024 In control: Commissioners Court
On agenda: 5/14/2024 Final action: 5/14/2024
Title: Issue Change Order for ITB #22-22 Brazoria County Road 59 Widening Project
Indexes: Expenditure
Attachments: 1. CO 7.Y.3 Sept 13, 2022 Court.pdf, 2. 0912-31-305 - Change Order 04 - Drainage Outfall Channel FINAL.pdf, 3. 2024-05-01-CR-58 Change Order.pdf, 4. Memo_CR 59_Change Order request justification.pdf

title

Issue Change Order for ITB #22-22 Brazoria County Road 59 Widening Project

end

body

Permission to issue change order to SER Construction Partners, LLC to provide additional 4-inch concrete riprap on the northern right-of-way of the outfall channel. This change order is necessary to ensure the project complies with the rules and regulations of Brazoria Drainage District No. 4, and adding $233,149.71 (1.85%) to the original contract for ITB #22-22 awarded by Commissioners Court Order 7.Y.3 dated September 13, 2022; and

 

Whereas, a copy of Change Order No. 4 in the amount of $233,149.71, a justification letter from the design engineer CobbFendley and a letter from Brazoria Drainage District No. 4 are attached; and

 

Whereas, funds for this expenditure are available via the 2024 Road & Bridge Budget. Federal funds, if available, may cover up to 80% of this change order.

 

Further, that a certified copy of this order be furnished to the County Engineer for distribution to all parties involved.