Permission to issue change order to SER Construction Partners, LLC to provide additional 4-inch concrete riprap on the northern right-of-way of the outfall channel. This change order is necessary to ensure the project complies with the rules and regulations of Brazoria Drainage District No. 4, and adding $233,149.71 (1.85%) to the original contract for ITB #22-22 awarded by Commissioners Court Order 7.Y.3 dated September 13, 2022; and
Whereas, a copy of Change Order No. 4 in the amount of $233,149.71, a justification letter from the design engineer CobbFendley and a letter from Brazoria Drainage District No. 4 are attached; and
Whereas, funds for this expenditure are available via the 2024 Road & Bridge Budget. Federal funds, if available, may cover up to 80% of this change order.
Further, that a certified copy of this order be furnished to the County Engineer for distribution to all parties involved.