File #: 15759    Version: 1
Type: Consent Agenda - Purchasing Department Status: Adopted
File created: 5/8/2024 In control: Commissioners Court
On agenda: 5/14/2024 Final action: 5/14/2024
Title: Change Order No. 2 for ITB #24-08 Hanson Parking Lot Drainage and ADA Sidewalk
Indexes: Change Order
Attachments: 1. Hanson Park Extra Asphalt Removal and Replacement

title

Change Order No. 2 for ITB #24-08 Hanson Parking Lot Drainage and ADA Sidewalk

end

body

Approve the expenditure for change order no. 2 for “ITB #24-08 Hanson Parking Lot Drainage and ADA Sidewalk” to Matula and Matula Construction of Lake Jackson, Texas, in the amount of $8,651.50 for the scope of work as per the attached.

 

In addition, expenditures will be funded with GoMesa funds.