Permission to issue change order to iCON GC, LLC to ensure the project complies with the rules and regulations of Brazoria County, and adding $557,496.61 (9.05%) to the original contract for ITB #23-82 awarded by Court Order I.7 at the December 12, 2023 Commissioners Court session; and
Whereas, a copy of applicable Change Orders in the amount of $557,496.61 and a justification letter from the resident engineer AECOM are attached; and
Whereas, funds for this expenditure are available via the 2025 Road & Bridge Budget. Federal funds, if available, may cover up to 80% of this change order.
Further, that a certified copy of this order be furnished to the County Engineer for distribution to all parties involved.