Approve the use of the TIPS cooperative contract number 23010402 for a job order contract for the “Juvenile Detention Center Split Systems Replacement project with APS Building Services of Houston, Texas in the amounts shown below.
In addition, the total expenditure of $434,972.99 for all proposals, will utilize ARPA Loss Revenue funds.
• 12.5 Ton Split System #1 - $51,835.58
• 12.5 Ton Split System #2 - $51,835.58
• 12.5 Ton Split System #3 - $51,835.58
• 6 Ton Split System #4 - $42,434.67
• 3 Ton Split System #5 - $24,858.23
• 6 Ton Split System #6 - $42,434.67
• 6 Ton Split System #7 - $42,434.67
• 6 Ton Split System #8 - $42,434.67
• 6 Ton Split system #9 - $42,434.67
• 6 Ton Split system #10 - $42,434.67
Further, that the County Judge be authorized to sign any and all documents necessary to execute said agreements on behalf of the County.