Engineering Services for the CR 179 Bridge Repair Project

end

body

Approve the additional expenditure of $86,399.00 to IEA Inc, to develop Plans, Specifications and Estimates required for the repair of CR 179 bridge at Drainage Ditch NBI No. 12-020-0-AA0771-001 “Project”; and

 

Whereas, the required repair work is the direct result of damages caused by construction activities conducted by EzeeFiber Utility Company; and

 

Whereas, the attached scope of work identifies the services necessary to support the design process for the Project.

 

Further, that the Court authorizes use of the Brazoria County Insurance Reserve (Fund 73000) for funding of this expenditure.

 

Further, that the County Judge or his designee be authorized to sign the attached Professional Services Contract and that a certified copy of this order be furnished to the County Engineer for distribution to all parties involved.