title
Amend Court Order 7.M.3 Dated November 9, 2021 Amend Professional Services Agreement for Colliers Engineering
end

body
Per the request of GrantWorks, Inc., of Austin, Texas, amend Court Order 7.M.3 dated November 9, 2021 as it pertains to the Field Collection and FEMA Elevation Certificate Form (Pre-Certificate) services under RFSQ #20-10 Elevation Certificates for Flood Mitigation cost increase of $150.00 per residence. The Court Order approved the pass-through cost of $150.00 to the homeowner.
In addition, if GrantWorks, Inc. can provide confirmation to the County that they have obtained approval from FEMA and/or TDEM, that the increased cost of $150.00 per certificate, will be covered by the Hazard Mitigation Program, the homeowners will not be responsible for the pass-through cost.
Further, a copy of this Court Order be delivered to the Purchasing Department, Floodplain Department and the Auditor’s Office.