Change Order No. 1 for ITB #24-05 Construction and Repair of the Quintana Beach Public Fishing Pier
end
body
Approve change order number 1 for “ITB #24-05 Construction and Repair of the Quintana Beach Public Fishing Pier”, to Shirley & Sons Construction Company, Inc., of Cleveland, Texas in the amount of $90,000.00, per the attached change order form.
The ADA ramp at the pier was damaged and then destroyed by Tropical Storm Alberto and Hurricane Beryl, respectively. The ramp will be constructed in the original location using larger timber pilings to provide added protection to the ramp during storms.
GoMESA funds will be used for the additional amount to rebuild the ADA ramp.