File #: 16630    Version: 1
Type: Consent Agenda - CDBG/HUD/Welfare Department Status: Adopted
File created: 12/27/2024 In control: Commissioners Court
On agenda: 1/14/2025 Final action: 1/14/2025
Title: Public Facility Agreement with the City of Alvin
Indexes: Plan Changes

title

Public Facility Agreement with the City of Alvin

end

body

The City of Alvin is requesting a 30-day extension for the 2023 Waterline Replacement Project deadline from December 31, 2024, to January 31, 2025 to allow for project completion.

 

Weather delays have impacted contractor’s ability to meet the deadline and finish work under the original time proposed.

 

Further, that the County Judge be authorized to sign Amendment on behalf of Brazoria County after final review of the District Attorney’s Office - Civil Division.